Walls, Slab, and Foundation on the Rise

Oct 30
2 min read

October brought exciting activity to the Lakewood ICC site as progress continues on both the main addition and the east side improvements.


With steel erection completed earlier this month, our framing team was able to install the exterior stud walls on the new addition. The walls were panelized offsite in 12' wide sections, swung into place with a crane, and secured to the building structure. It was a very efficient process, with all of the walls set in about two days. Crews are now detailing out the stud walls in preparation for the air and vapor barrier.


At the end of the month, we also poured the second floor slab on deck. Getting the concrete placed in just one day was a large effort. Once it cures, we’ll be able to use our robot to print layout on the floor for framing and MEP. Our focus on the new addition now turns to installing underground utilities, setting the roof and drying in the building, and gearing up for second floor interior work.


On the east side, good progress has been made on the electrical room addition. Our concrete trade partner, VanLaan, has poured the first sequence of footings for the retaining wall and electrical room foundations. Before that work began, our ground improvement trade partner, Menard, was on site installing helical piers beneath the footing elevations. These piers help stabilize the soil in this area and give the foundations a solid platform to bear on. Once the first sequence of foundation walls is complete, our excavating crew and Menard will return to prepare for the second sequence of foundations.

We are reaching an exciting stage of the project where the building is really starting to take shape. With both exterior and interior work underway on the new addition, the site is visibly changing day by day. EV is excited to continue bringing this project to life!