Preparing to go Vertical
Foundation work for the building addition is making strong progress as the project continues to move steadily forward. Last week, VanLaan successfully poured the remainder of the west foundation wall, marking another significant milestone in the early structural phase of construction. With that portion complete, crews are now turning their attention to forming and pouring the interior pier pads and elevator pit, two critical components that will help support the building’s fu
May 20


Deep Foundations
Construction activity continues to move forward steadily, with several key milestones achieved over the past week and more groundwork being laid for upcoming phases. On Monday, VanLaan Concrete successfully completed the next portion of the foundation wall. This marks another important step in establishing the structural base of the project, keeping foundation work on track and aligned with the overall schedule. Meanwhile, the EV Sitework Division has been actively preparing
Mar 19