top of page


Structural Steel Brings a New Look to Lakewood ICC
August brought an exciting milestone to the Lakewood ICC project as structural steel officially began going up. With FCC mobilizing to the site, the project is entering a highly visible phase of construction that will quickly transform the look of the new addition. In preparation for steel erection, crews have completed demolition of the existing façade where the new addition will connect to the current building. The new masonry stair and elevator towers are also complete, pr
Aug 31


Construction is Moving Above Ground
The past several weeks have brought a noticeable increase in activity at the 588 Lakewood project, with multiple trade partners working on site each day as construction continues to gain momentum. After months of site preparation and foundation work, the project has officially entered one of its most exciting phases—vertical construction. One of the first major milestones was the completion of a temporary interior wall within the existing building. While not highly visible fr
Jul 21


Preparing for the Next Big Phase of Construction
The project is reaching an exciting milestone as foundation work for the new addition enters its final stages this week. After months of site preparation, excavation, and concrete work, the focus is now shifting toward vertical construction — the point where the project will begin taking visible shape above ground. Later this month, crews will begin the façade demolition of the existing exterior wall where the new addition will connect to the current facility. Before any demo
Jun 18


Preparing to go Vertical
Foundation work for the building addition is making strong progress as the project continues to move steadily forward. Last week, VanLaan successfully poured the remainder of the west foundation wall, marking another significant milestone in the early structural phase of construction. With that portion complete, crews are now turning their attention to forming and pouring the interior pier pads and elevator pit, two critical components that will help support the building’s fu
May 20


Deep Foundations
Construction activity continues to move forward steadily, with several key milestones achieved over the past week and more groundwork being laid for upcoming phases. On Monday, VanLaan Concrete successfully completed the next portion of the foundation wall. This marks another important step in establishing the structural base of the project, keeping foundation work on track and aligned with the overall schedule. Meanwhile, the EV Sitework Division has been actively preparing
Mar 19
bottom of page

